aof.sorular.net
Busıness Decısıon Models
Busıness Decısıon Models Deneme Sınavı
Busıness Decısıon Models Deneme Sınavı Sorusu #1369553
Busıness Decısıon Models Deneme Sınavı Sorusu #1369553
For the given cost matrix, how much is the total transportation cost calculated by Northwest Corner Method solution? (all costs in Turkish liras)
157 |
159 |
145 |
168 |
175 |
Yanıt Açıklaması:
The initial basic feasible solution obtained in the table below has the basic variables given below.
x11 = 10, x21 = 1, x22 = 3, x32 = 4, x42 = 4, x43 = 5,
The objective value for this solution, which is the total transportation cost is 168 TL.
Z = 5× 10 + 1 × 7 + 3 × 5 + 4× 6+ 4 × 6+ 5 × 6 = 168 TL.
Yorumlar
- 0 Yorum