What is the term used to refer to the risk of loss resulting from inadequate or failed internal processes, people and systems or from external events?
Quantifying Risk |
Liquidity Risk |
Operational Risk |
Credit Risk |
Market Risk |
Yanıt Açıklaması:
With the enhancement of the Basel-II, the Basel Committee added a new class of risk into the calculation of risk-based capital charges. The Committee defined the operational risk as the “risk of loss resulting from inadequate or failed internal processes, people and systems or from external events”. The correct answer is C.