I.Time-based system
II. Piece based system
III. Premium based system
Which of the systems above ignores productivity?
Only I |
Only II |
Only III |
I and II |
I, II and III |
Yanıt Açıklaması:
Under the time-based system, the important point is the time that employee spends at work. The measure of time can be the hour, day, week or month. Under this system, productivity is ignored, only time is considered.