Cost And Management Accountıng Deneme Sınavı Sorusu #1391570

Direct labors in XYZ Company have worked for 43,200 hours in order to produce 8,000 trays. The actual wage rate that the Company has incurred for each hour is 15TL, although the standard wage rate was 13TL for the year. Can you calculate the direct labor price variance?


28,800TL

32,000TL

43,200TL

51,200TL

86,400TL


Yanıt Açıklaması:

Direct labor price variance = (Actual rate - Budgeted rate) x Actual labor hours worked

Direct labor price variance = (15 - 13) x 43,200 = 86,400TL (U)