"Activity....................." Which of the following best completes the statement above?


allocates each unit if management uses indirect labor hours or machine hours

traces the direct costs as it is more reliable than allocating the indirect costs

increases the direct costs’ share in total cost decreasing the reliability of cost assignment

is defined as any event or task that is carried out in order to meet a specific goal.

is ignored in refined costing system for a more detailed analysis of cost assignment


Yanıt Açıklaması:

Activity can be defined as any event or task that is carried out in order to meet a specific goal, such as designing, assembling, testing, etc.