There are four phases in EPS systems:
I.Enterprise Resource Planning (ERP)
II.Material Requirements Planning (MRP)
III.Manufacturing Resource Planning (MRP II)
IV.Closed Loop Material Requirements Planning (MRP-CL)
Which of the followings gives the correct order of the phases in the Evaluation of the ERP systems?
II, IV, III, I |
IV, II, I, III |
II, III, I, IV |
IV, I, II, III |
I, III, II; IV |
Yanıt Açıklaması:
Phase I - Material Requirements Planning (MRP), Phase II - Closed Loop Material Requirements Planning (MRP-CL); Phase III – Manufacturing Resource Planning (MRP II); Phase IV - Enterprise Resource Planning (ERP).