Statıstıcs I Deneme Sınavı Sorusu #822432
A company works with two supplier firms for the same raw material. The first firm's late delivery probability on a given day is 0.05, whereas for the second firm this probability is 0.07. In addition, both firms' late delivery probability on given day is 0.04. What is the late delivery probability of at least one of the firms to company on given day?
0.05 |
0.06 |
0.07 |
0.08 |
0.09 |
Yanıt Açıklaması:
P(OUY) = P(O) + P(Y) - P(O∩Y) = 0.05 + 0.07 - 0.04 = 0.08