AÖF Soru Bankası
İSL357U

Operatıons Management (ENG)

Deneme Sınavı Soruları

  • 20 soru
  • Cevap anahtarı açık: çöz, sonucunu gör
0 doğru · 0 yanlış · 20 kaldı
  1. 1

    Which is FALSE about successful implementation of the MRP system?

  2. 2

    What does " an information system designed to integrate internal and external members of the supply chain" stand for?

  3. 3
    Which option shows the chronological order of the transformation process in time ?
  4. 4

    I. To keep customer satisfaction as high as possible. 

    II. To ensure the best use of material, labor and production tools.

    III.To consider customer orders.

    IV. To keep the level of investment in the material at the desired level. 

    V.To consider sales forecasts.

    Which of the above show the purpose of the master production schedule?

  5. 5

    Which of following is not correct?

  6. 6

    Which of the following is the approach of roughly estimating and determining the required level of capacity problems in order to realize the master production schedule?

  7. 7

    Which of the following is a transformed form of the master production schedule into workloads?

  8. 8
    1. value
    2. value stream
    3. flow
    4. pull
    5. perfection

    Which of the given above are main principles of lean systems?

  9. 9

    The phenomena that small changes in customer demand at the end of the supply chain propagate to the beginning of the supply chain with significantly increased order variations is called .............

  10. 10
    1. Supplier 
    2. Intermediaries
    3. Third-party service providers 
    4. Customers

    Which of the above are included in the supply chain? 

  11. 11

    I.Transportation 

    II.Inventory

    III.Waiting

    IV.Motion

    V.Overproduction

    VI.Overprocessing 

    What are the types of waste that were defined originally by Taiichi Ohno in lean systems?

  12. 12
    1. Lean systems focus on producing exactly what the customer wants
    2. Lean tries to improve value with less work to provide perfect value to the customer with a perfect value creation process with zero waste
    3. “Continuous improvement” and “respect for people” are the two main pillars of lean systems
    4. Leaders of lean systems often spend their time advising and actively working with their workers to identify problems and to improve their systems by eliminating wastes

    Which of the given is correct for lean systems?

  13. 13

    Choose the option that completes the following sentence correctly.

    "Manufacturing Resource Planning is mentioned in the literature with the abbreviation MRP II to avoid confusion with the .........."

  14. 14

    What does "a modeling tool used to evaluate independent decisions that must be made in sequence" stand for?

  15. 15

    Which of the following is not the end result of Business Process Reengineering?

  16. 16

    Which of the activities below is not a part of  Operation Management?

  17. 17

    Which of the following statements is not  a main objective of operations/production management?

  18. 18

    Which of the following characteristics of product layout is true?

  19. 19

    Which of the following is not listed among the general characteristics of the product layout?

  20. 20
    Which phase are DVD and flash disks in?
Bir şıkka dokun; doğru cevap hemen görünür.
Yeni yılların sınavlarını da çözOperatıons Management (ENG) dersinin tüm sınavları, cevap anahtarları, süreli mod ve yanlış analizi uygulamada.Uygulamada aç