Project Management (ENG)
Deneme Sınavı Soruları
- 20 soru
- Cevap anahtarı açık: çöz, sonucunu gör
- 1
What does AOA stand for?
- 2
All of the following is one of the four "M"s of resource management, except...
- 3
Which information below is true about the comparison between AOA and AON?
- 4
............................. is a non-simple, non-repetitive, one-time effort limited by budget, schedule and performance specifications designed to meet customer needs
According to the definition, which of the following should come to the dotted point?
- 5
- It predicts the upcoming resource requirements of the company.
- it collects data on sales, schedules, activities, progress of the project, and launches.
Which of the following resource management software tool does the things described above?
- 6
Which of the followings can be an example to a project?
- 7
"In this phase, the level of effort rises. A more formal set of plans are established to determine when the project will be scheduled, what the budget will be and what quality level should be maintained. Then, individual tasks and requirements of the project are defined."
Which of the following is defined as one of the phases which form the project life cycle in the paragraph above?
- 8
I. Compute the variance of each activity by using formula
II. Calculate the expected project duration
III. Calculate the expected value of each activity
Which of above is among the major steps of PERT?
- 9
Which of the following is a type of organizational structure in which team members report more than one project manager?
- 10
PERT is pessimistic about the variance in the project duration. Therefore, if there are multiple critical paths in the project network, which critical path must be chosen to determine the project duration and the variance of the project duration?
- 11
Which of the following is the first thing in a project to satisfy customers?
- 12
By which of the following formulas is free slack computed?
- 13
Which of the following is not a project?
- 14
Which of the following is wrong according to the difference between projects and ordinary work?
- 15
Which of the following is not one type of project that the Program Evaluation and Review Technique and Critical Path Method can be applied to?
- 16
In RACI model; who does Responsible (R) refer to?
- 17
In which of the following techniques are activities broken into pieces and resource requirements estimated for these small pieces while estimating resources?
- 18
Which of the following statements is false?
- 19
Which of the followings are the factors by which the outcome of a project is evaluated?
- Personnel
- Cost
- Schedule
- Performance
- 20
...........is the implementation of knowledge, skills, tools, and techniques to project activities to accomplish project goals.
Which term can be used in the blank?