Project Management (ENG)
Deneme Sınavı Soruları
- 20 soru
- Cevap anahtarı açık: çöz, sonucunu gör
- 1
Which of the following is not a part of the project closure plan?
- 2
The task of the ..................... is to ensure that everyone in the project team has what they need to do their job well.
Which of the following should come to the dotted point according to the continuation of the sentence?
- 3
Parker (2008) indicated four styles of team members where each contributed in different ways to the success of the team. According to him, which of the following members questions the goals, methods, and even the ethics of the team, is willing to disagree with the leader and others, and encourages the team to take well-conceived risks?
- 4
Which of the following is used to offset the impact of a risk on the scope, time, cost, or quality of a project?
- 5
Project Team A agrees to work with Supplier X. The data shows that Supplier X failed to deliver in time, 3 times in the 45 projects they worked together. What is the Expected Monetary Value if the impact on the project is $60,000?
- 6
Parker (2008) indicated styles of team membersParker (2008) indicated styles of team memberswhere each contributed in different ways to the success ofthe team.
According to Parker’s study:
• A _________ is a task-oriented team member whoenjoys providing the team with good technicalinformation and data, does his or her homework, andthen pushes the team to set high performance standardsand to use their resources wisely.
Which one of the following fits to the definition above? - 7Parker indicated four styles of team members where each contributed in different ways to the success of the team. Based on these styles which is a goal-directed member but is flexible and open to new ideas and work outside his or her defined role?
- 8
Which value is actual spending by the status date, in other words, the real (current) cost of the project?
- 9
Which of the following is not one of the Typical Responsibilities of the Project Manager in the Project Organization?
- 10
Which of the following is not among the steps you should follow in order to evaluate and control a project?
- 11
____________ is budget of an activity or a project, and it is also called the baseline cost which means the cost of the baseline plan. It is calculated at the end of the planning phase. Of course, each activity has its own budget. Project budget is the summation of all activity budgets and other expenditures such as setup cost, fixed cost, and general expenses.
Which option below best completes the sentence?
- 12
Which of the following is an explanation of how you plan to implement the project risk management plan?
- 13
Which of the following is a review of the project after the closure or acceptance of the project?
- 14
At which phase of a project, the level of effort is the highest?
- 15Which of the following is not one of the challenges that resource allocation has?
- 16
Which of the followings organizes and defines the total scope of the project, and represents the work specified in the current approved project scope statement?
- 17
Which of the following phases of project life cycle typically takes the longest?
- 18
A good staffing management plan consists of all of the following, except...
- 19
Which of the following is NOT one of the differences between AOA ve AON?
- 20
"In this technique, activities are broken into pieces and resource requirements
are estimated for these small pieces"Which of the following is the definition of the technique given above and used to estimate resources?