Project Management (ENG)
Deneme Sınavı Soruları
- 20 soru
- Cevap anahtarı açık: çöz, sonucunu gör
- 1
The project management plan usually includes sub-plans. Which of the below is NOT one of them?
- 2
Which of the followings is the main purpose the project closure?
- 3
I. Obtain client acceptance
II. Transition deliverables to owner
III. Close out contract obligations
IV. Capture lessons learned
V. Document final project financials
Whcih topic areas given above should be covered in the project checklist? - 4
Which one of the following is not required to develop the idea of partnership between the project manager
and the team? - 5
Which of the following can be listed among the cons of becoming a Project Manager?
- 6
I. Contractual obligations are fulfilled.
II. Procurement documents are completed.
III. Transfer contracts between project and operation teams are made.
IV. Resources are reallocated.
Among the statements given above, which are true for project closing process? - 7
Parker (2008) indicated styles of team members
where each contributed in different ways to the success of
the team.According to Parker’s study:
• A _________ is a task-oriented team member who
enjoys providing the team with good technical
information and data, does his or her homework, and
then pushes the team to set high performance standards
and to use their resources wisely.Which one of the following fits to the definition above?
- 8
Which of the below is NOT one of the topic areas to be covered in the project checklist?
- 9
__________ is the action of leading a group of people or an organization to achieve the goals. Which of the followings completes the blank?
- 10
Which of the following is achieved by dividing the rest of earned value into the rest of the budget?
- 11
- Engineering
- Quality
- Finance
Which of the responsibilities above does a project manager have?
- 12
Which value, whose unit is not man-hours but monetary unit, shows the cost for the work performed by the status date?
- 13
In which of the following topic areas; documenting the project team’s experience-related activity will enable future projects to avoid some mistakes and challenges faced by the existing team?
- 14
Which of the following is a type of organizational structure in which team members report more than one project manager?
- 15
Which of the followings is not a project?
- 16Which of the following is a similarity between AON and AOA diagramming?
- 17
What is the name of the document that explains when and how people will be part of and dismissed from a project?
- 18
I. Introduction
II. Staffing requirements
III. Staff assignments
IV. Reassignment partsWhich of the above are components of a good staffing management plan?
- 19
Which of the following is not one of the components of the network?
- 20
In which step of the Resource management are resources assigned to the specific activities in the project schedule?