Which of the following is not one of the cons of being a project coordinator?
- 2
Which of the following is not required to develop the idea of partnership between the project manager
and the team ? - 3
- Technical performance analysis
- Risk audits
- Reserve analysis
Which of the techniques above does data analysis in monitoring risk process include?
- 4
Which of the following questions is not a good one to Evaluate whether the results of the project, decisions, and deliveries meet the expectations of the stakeholders?
- 5
Which of the following is true about "Tardiness"?
- 6
Which of the following is to obtain a comprehensive list of individual project risks and sources of overall project risk?
- 7
Who is the person that leads a project from its phases of initiation to closure in the project life cycle?
- 8
Which of the following is not a process of a Project Life Cycle?
- 9
Which of the following does not fit to the attributesof the project manager that determine their roles ina project?
- 10
Which of the following shows the cost for the work performed by the status date?
- 11
Which of the following analysis is the process of numerically analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives?
- 12
Which of the quantitative risk analysis technique below is related to measuring how the system reacts under various conditions?
- 13
Which of the following is not true about "Variances" in a project?
- 14
It is generally assumed that modern project management began with the .......?
- 15
Which of the following is wrong for work packages?
- 16
Which of the following cannot be claimed to be one of the top five tips for resource forecasting in project management?
- 17Which of the following is NOT an example for a project?
- 18
Which one is not the reason why importance of project management is increasing?
- 19
Which of the following statements can be said about resource management software?
- 20
The steps of the PERT analysis are presented scratchily as follows. Which of the following represents the right sequences of these processes about the PERT analysis?
- Compute the variance of each activity.
- Determine three estimates; optimistic “a”, modal “m”, and pessimistic “b” durations for each activity.
- Calculate the expected value for each activity by using a, m, and b.
- Similar to expected duration, calculate the variance of the project as the sum of individual variance of activities on the critical path.
- Calculate the expected project duration, Tx.
- In addition to expected project duration, the probability of finishing the project within specified time limits can be calculated.