AÖF Soru Bankası
İSL358U

Project Management (ENG)

Deneme Sınavı Soruları

  • 20 soru
  • Cevap anahtarı açık: çöz, sonucunu gör
0 doğru · 0 yanlış · 20 kaldı
  1. 1

    Which of the following is not one of the cons  of being a project coordinator?

  2. 2

    Which of the following is not  required to develop the idea of partnership between the project manager
    and the team ?

  3. 3
    1. Technical performance analysis
    2. Risk audits
    3. Reserve analysis

    Which of the techniques above does data analysis in monitoring risk process include?

  4. 4

    Which of the following questions is not a good one to Evaluate whether the results of the project, decisions, and deliveries meet the expectations of the stakeholders?

  5. 5

    Which of the following is true about "Tardiness"?

  6. 6

    Which of the following is to obtain a comprehensive list of individual project risks and sources of overall project risk?

  7. 7

    Who  is the person that leads a project from its phases of initiation to closure in the project life cycle?

  8. 8

    Which of the following is not a process of a Project Life Cycle?

  9. 9

    Which of the following does not fit to the attributesof the project manager that determine their roles ina project?

  10. 10

    Which of the following shows the cost for the work performed by the status date?

  11. 11

    Which of the following analysis  is the process of numerically analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives?

  12. 12

    Which of the quantitative risk analysis technique below is related to measuring how the system reacts under various conditions?

  13. 13

    Which of the following is not true about "Variances" in a project?

  14. 14

    It is generally assumed that modern project management began with the .......?

  15. 15

    Which of the following is wrong for work packages?

  16. 16

    Which of the following cannot be claimed to be one of the top five tips for resource forecasting in project management?

  17. 17
    Which of the following is NOT an example for a project?
  18. 18

    Which one is not the reason why importance of project management is increasing?

  19. 19

    Which of the following statements can be said about resource management software?

  20. 20

    The steps of the PERT analysis are presented scratchily as follows. Which of the following represents the right sequences of these processes about the PERT analysis? 

    1. Compute the variance of each activity. 
    2. Determine three estimates; optimistic “a”, modal “m”, and pessimistic “b” durations for each activity.
    3. Calculate the expected value for each activity by using a, m, and b.
    4. Similar to expected duration, calculate the variance of the project as the sum of individual variance of activities on the critical path.
    5. Calculate the expected project duration, Tx.
    6. In addition to expected project duration, the probability of finishing the project within specified time limits can be calculated.
Bir şıkka dokun; doğru cevap hemen görünür.
Yeni yılların sınavlarını da çözProject Management (ENG) dersinin tüm sınavları, cevap anahtarları, süreli mod ve yanlış analizi uygulamada.Uygulamada aç