  1. 1

    I.   The Risk Records
    II.  Assumption Log
    III. Stakeholder Register

    Which of the above are inputs for qualitative risk analysis?

  2. 2

    Which of the followings is a project evaluation and monitoring method?

  3. 3

    Which of the following includes reducing the likelihood of risk occurring or the effect of damage?

  4. 4

    Which of the following summarizes the resources required for project closing activities?

  5. 5

    In a partnership, each member of the project team is responsible for the project’s outcomes and the current situation, whether it is positive or shows evidence of problems. What is this condition called?

  6. 6

    Which of the followings is the formula to calculate BCWP?

  7. 7

    What is calculated as multiplying workforce by duration?

  8. 8

    Which of the following is consisted of a group of people who have come together to carry out activities that contribute to achieving the goal of a common task?

  9. 9

    Which of the following presents the risk identification technique that include the questions about the reasons of the risks and the conditions where the risk turn into a problem?

     
  10. 10

    "The project manager should also consider the impact thresholds for the risks. If the impacts exceed the specified thresholds, emergency plans are implemented. Thresholds may be in terms of money, duration, or number of resources based on tolerance." 

    According to this information, which of the scenarios below requires an emergency plan to be implemented?

  11. 11

    Which of the following is used to describe the effect of variables by representing each risk and its impact by a bar?

  12. 12

    Which one of the following is one of the pros becoming a project manager?

  13. 13

    Which one of the following does not fit to the attributes of an effective project manager defined by Meredith and Mantel (2009)?

  14. 14

    What is the visual representation of the project’s content and goals in project scheduling?

  15. 15

    ....................A sequence of connected, dependent activities.

    According to Constructing a Project Network Which of the following should come to the dotted spot?

  16. 16

    "... is the time phased processing of operations subject to precedence interactions, time constraints, and resource constraints in order to achieve particular goals."

    Which of the following would best fill the blank space above?

  17. 17
    Which of the following is not mentioned in the summary desrciption of a project?
  18. 18

    Which of the followings are the reasons why importance of project management is increasing?

    1. Compression of the Product Life Cycle
    2. Knowledge Explosion
    3. Increased Customer Focus
    4. Corporate Downsizing
  19. 19

    How many kinds of data are required to describe a project?

  20. 20

    Which of the following is not one of the techniques and tools used to estimate the resources for each activity in the project schedule? 