  1. 1

    Which of the following is not among the tools that can be used to perform qualitative risk analysis?

  2. 2

    Which of the following is not used for quantitative risk analysis?

  3. 3

    Which of the following includes reducing the likelihood of risk occurring or the effect of damage?

  4. 4

    I. Scope
    II. Schedule
    III. Costs
    IV. Quality
    V. Marketshare

    Which of the sub-plans above does the project management plan include?

  5. 5

    Which of the below is a summary information about the effort, timing, and desired benefit related to the project closure?

  6. 6

    Which of the below is NOT trues about Earned Value Analysis (EVA)?

  7. 7

    Which of the following indicators  shows the performance to be done after the status date in order to meet the project budget and the schedule targets? 

  8. 8

    Which of the following is explaining what to do and what not to do in future projects?

  9. 9
    1. Removal
    2. Transferring risk and insurance
    3. Mitigation
    4. Acceptance

    Which of the strategies above can be used to avoid risk according to the situation of project and risk?

  10. 10

    Which of the following is one of the tools or techniques of quantitative risk analysis?

  11. 11

    In order to avoid negative risks, Project Team A decides to work with Supplier X with whom they have worked before. This strategy is an example of ...............?

  12. 12

    What is tardiness?

  13. 13

    With which of the risk avoiding strategy the risk does not disappear but shifts to the third party?

  14. 14

    Which of the following process groups involves Work Breakdown Structure (WBS)? 

  15. 15

    Which of the followings is a point with zero duration that indicates a cumulative sequence of events while performing the project?

  16. 16

    As many managers have said, among all the resources, which is the most important asset of the
    companies?

  17. 17

    Which of the following is not one of the project characteristics?

  18. 18

    Which of the below occurs when there is a prevalent predecessor for two or more operations?

  19. 19

    Which of the followings is one of the kinds of data required to describe a project?

    1. Activity information
    2. Variable information
    3. Precedence relationships
    4. Time information
  20. 20

    Which of the following is not true about "project management"?