  1. 1

    What are the two outputs of the initiating process group?

  2. 2
    Which of the followins are stated as part of attributes of a project? I. A project always includes established sets of routines. II. A project states certain specific objectives III. Projects are permanent activities. IV. A project uses various resources
  3. 3

    In project management process which process involves detailing the project scope, time frames, resources, and risks?

  4. 4

    The stages of design, production and implementation are included in which of the phases of a project life cycle?

  5. 5

    ................, founded in 1969, is a professional organization for project management specialists and its services include the development of standards, research, education, publication, networking opportunities in local chapters, hosting conferences and training seminars, and providing accreditation in project management? 

  6. 6

    Which of the following is one of the three factors used in the evaluation of the outcomes of a project?

  7. 7

    Which of the followings are attributes of a project?

    I. A project states certain specific objectives (schedule and cost).

    II. Projects are temporary activities.

    III. A project may be unique.

    IV. A project uses various resources to conduct project activities.

  8. 8

    In which of the following process groups is "Work Breakdown Structure" created?

  9. 9

    Which of the following is a method for dividing the overall project into smaller elements that is called work packages?

  10. 10

    Which of the followings is carried out in Initiating Process Group?

  11. 11
    Which of the phases of project life cycle involves obtaining feedback from customers?
  12. 12

    What are the three main factors generally used to evaluate the outcomes of a project? 

  13. 13

    Which of the following is not one of the ways project management methodology helps the project manager?

  14. 14

    "A project is usually a one-time activity with a well-defined set of expectations and ...................."

    Which of the following could be put in the blank above to complete it appropriately?

  15. 15

    What process consists of tracking and reviewing the performance of the projects? 

  16. 16

    Which of the followings is done in Monitoring and Controlling Process Group?

  17. 17

    Which of the followings are the factors by which the outcome of a project is evaluated?  

    1. Personnel
    2. Cost
    3. Schedule
    4. Performance
  18. 18

    Which of the following includes the stages of design, production and implementation?

  19. 19

    Which of the following is false regarding projects?

  20. 20

    Which of the following is not one of the reasons why the importance of project management is increasing?