What are the expected results over the course of a project called (e.g. making a list of specifications during a furniture design project)?
- 2
Which of the followings is an activity that has more than one activity immediately preceding it (more than one dependency arrow flowing to it)?
- 3Which of the following is FALSE according to this figure?

- 4
In projects start times is generally ....?
- 5
Which of the following is among the questions that a project objective can answer?
- What?
- When?
- How much?
- 6
Which of the following is not one of the project characteristics?
- 7Which of the following is not one of the tasks that a work package manager is responsible for?
- 8Which of the following is TRUE about the following figure?

- 9
Which of the following statements is not true regarding a project?
- 10
Which of the followings present the obeys about the drawing an activity-on-node project network?
- A network commonly flows from left to right.
- When all preceding connected activities have been performed, a new activity can start.
- Precedence relations and flows are represented by arrows on networks, arrows can also cross over each other.
- Any loop of activities is not allowed in the network.
- There should be no conditional statements between activities.
- 11
Which of the following is the term that defines one begins with the last project activity/ies and goes along the other sequential activity/ies through the network through the first activity/ies?
- 12
Which of the following is not a project?
- 13
Which of the followings is a point with zero duration that indicates a cumulative sequence of events while performing the project?
- 14
Which of the followings is NOT true for the characteristics of a project?
- 15
............................. definition is the process of developing a detailed description of the project and product.
Which of the following should come to the dotted point according to the continuation of the sentence?
- 16
Which of the followings is included in the checklist to guarantee that scope definition is complete?
- Project objective
- Milestones
- Technical Requirements
- Deliverables
- 17
Project scope is the keystone engaging all elements of a project plan. To guarantee that scope definition is complete, there is a checklist. Which of the following is the "significant point or event in the project" from these checklist?
- 18
Which of the following behaves as a link, but it is not a “real” activity, so it does not have time duration?
- 19
............................. is a non-simple, non-repetitive, one-time effort limited by budget, schedule and performance specifications designed to meet customer needs
According to the definition, which of the following should come to the dotted point?
- 20
Which of the following can be defined as the process of developing a detailed description of the project and product?