Project Management (ENG)
Ünite Sınavı Soruları
- 20 soru
- Soru metinleri açık; şıklar ve cevap anahtarı uygulamada
- 1
The members of Project Team A have difficulty using their resource management software since the software (1) is not fully compatible with the software used in the company and (2) does not allow them to predict the upcoming resource requirements of the company.
In what aspects does the resource management software used by Project Team A fail to meet the criteria for selecting resource forecasting software?
- 2
Which of the followings is NOT one of the the Four M’s, which is a common framework for defining the resources available for a project?
- 3
Which of the following is not included in a good staffing management plan?
- 4
What kind of tools are Microsoft Project and Hub Planner for a project management process?
- 5
What is the RACI model used for?
- 6According to Leankor and Bailey, which of the following should be done first to get optimal performance from the resources?
- 7
"Resource management .............................."
Which of the following most appropriately completes the sentence above?
- 8
Which of the following is an advantage of the resource allocation?
- 9
At what step of resource management, can the dates of the tasks be delayed in order to overcome the overallocation of resources?
- 10
There are five techniques and tools to estimate the resources for each activity in the project schedule. Which of them lets you analyze the “what-if” scenarios and can be very useful to estimate the resources required for future projects?
- 11
In which of the following techniques are activities broken into pieces and resource requirements estimated for these small pieces while estimating resources?
- 12
As many managers have said, among all the resources, which is the most important asset of the
companies? - 13
In ............... step, resources are assigned to the specific activities in the project schedule whereas in ............... step the required resources are summed with respect to outputs of the previous step?
- 14
In RACI model; who does Responsible (R) refer to?
- 15
"In the stage of Resource Aggregation, ....................................."
Which of the following most appropriately completes the sentence above?
- 16
All of the following is one of the four "M"s of resource management, except...
- 17
- when and how people will be part of and dismissed from a project is explained.
- the necessary information about training, reward mechanism, and reassigning process for the resources is provided.
In which of the followings are the works described above done?
- 18
Which one of the following is the first step of resource management?
- 19
Which one of the below is about secondary resources?
- 20
What is the correct order for the steps of resource management?
I. Estimate the required quantity of each resource
II. Apply the techniques to aggregate and level the resources
III.Define the necessary resources
IV.Classify the resources