- Estimating cash flow
- Adding up the discounted cash flows to obtain NPV
- Discounting cash flows by an appropriate discount rate
- Projecting the risk differences of different projects
Which of the following are the steps of calculating net present value?
I and III |
II and IV |
I, II and III |
I, II and IV |
II, III and IV |
Yanıt Açıklaması:
Tthere are three steps of calculating NPV:
- Estimating cash flows,
- Discounting cash flows by an appropriate discount rate,
- Adding up the discounted cash flows to obtain NPV.
The correct answer is C.