Busıness Fınance Iı Deneme Sınavı Sorusu #1033415

  1. Estimating cash flow
  2. Adding up the discounted cash flows to obtain NPV
  3. Discounting cash flows by an appropriate discount rate
  4. Projecting the risk differences of different projects

Which of the following are the steps of calculating net present value?


I and III

II and IV

I, II and III

I, II and IV

II, III and IV


Yanıt Açıklaması:

Tthere are three steps of calculating NPV:

  1. Estimating cash flows,
  2. Discounting cash flows by an appropriate discount rate,
  3. Adding up the discounted cash flows to obtain NPV.

The correct answer is C.