“Is it possible to set up the proposed system in the determined time interval?” Which feasibility step asks this question?
Technical feasibility |
Operational feasibility |
Economic feasibility |
Scheduling feasibility |
Legal feasibility |
Yanıt Açıklaması:
Scheduling feasibility: Is it possible to set up the proposed system in the determined time interval? For this purpose, project activity scheduling techniques like PERT and Gantt charts are used to determine whether it is feasible to setup system on time.