Project Management (ENG)
Deneme Sınavı Soruları
- 20 soru
- Cevap anahtarı açık: çöz, sonucunu gör
- 1
It is generally assumed that modern project management began with the .......?
- 2
I. Predictions provided by an experienced person
II. Estimates provided by the results of simulation scenarios
III. Customer requirements
Which strategy above can be used to determine the duration estimates necessary for PERT?
- 3
What is the name of the document that explains when and how people will be part of and dismissed from a project?
- 4
As many managers have said, among all the resources, which is the most important asset of the
companies? - 5
Which of the followings is NOT one of the components of a network?
- 6Which of the following is FALSE according to this figure?

- 7
Which of the following is true about "Activity on Arrow (AOA)" and "Activity on NodeAON)"?
- 8
Which of the followings are the tru definitions about "project scheduling"?
- It is a time based processing.
- It considers the time constraints.
- It considers constraint the resource constraints.
- Precedence interactions are important issues about it.
- 9
All of the following are the stages of the fundamental network assessment of the project, except...
- 10Which of the following statement is true about "CPM"?
- 11
Which of the following is a program rather than a project?
- 12
There are three phases of Scope Management. Which of the following is the phase where the objectives and goals of the project are defined, tasks and resources are allocated, and budget & time constraints are established, and lastly the limitations of the project are identified?
- 13Which of the following is not true about "project"?
- 14
Which of the below is NOT one of the components of the framework for resource management?
- 15Which of the following is not one of the reasons why importance of project management is increasing?
- 16
A raw food workshop might be organized between January 25 and February 3. However, a bridge project for Bosphorus can take four years.
Which attribute of a project does the above example refer to?
- 17
According to the figure, how many days are needed to do activity E?

- 18
................, founded in 1969, is a professional organization for project management specialists and its services include the development of standards, research, education, publication, networking opportunities in local chapters, hosting conferences and training seminars, and providing accreditation in project management?
- 19"Verify scope" process is part of which process group?
- 20
The steps of the PERT analysis are presented scratchily as follows. Which of the following represents the right sequences of these processes about the PERT analysis?
- Compute the variance of each activity.
- Determine three estimates; optimistic “a”, modal “m”, and pessimistic “b” durations for each activity.
- Calculate the expected value for each activity by using a, m, and b.
- Similar to expected duration, calculate the variance of the project as the sum of individual variance of activities on the critical path.
- Calculate the expected project duration, Tx.
- In addition to expected project duration, the probability of finishing the project within specified time limits can be calculated.