    What does "tardiness" mean?

  2. 2

    Which of the following are the true expressions about reducing the risk uncertainty?

    1. You need to eliminate the negative consequences.
    2. You must identify the likelihood and consequences of the risk.
    3. It is important to consider the risk's impact, and possible causes.
    4. Risks can not affect the scope, cost, time, and/or quality of projects.
    5. It is important to standardize the impact of risks in a common language for sharing the information to the stakeholders.
       
  3. 3

    In which of the following topic areas; documenting the project team’s experience-related activity will enable future projects to avoid some mistakes and challenges faced by the existing team?

  4. 4

    Which of the following topic areas covered in the project checklist?

    1. Transition deliverables to owner
    2. Capture lessons learned
    3. Celebrate
    4. Update team resumes
  5. 5

    Which of the following has to be accomplished before the team attempts to close the project?

  6. 6

    "The lessons learned process helps in evaluating processes, tools, and techniques that worked either well or poorly on the project"

    Which of the following is the step of portmortem review mentioned above?

  7. 7

    Which of the following involves documenting project records and deliverables as a formal archive for the organization?

  8. 8

    "The Postmortem Review................"

    Which of the following most appropriately completes the sentence above?

  9. 9

    What means delay?

  10. 10

    What is the master plan, which has been executed at the end of the planning phase of a project?

  11. 11

    Which one of the following is one of the cons becoming a project manager?

  12. 12

    Which metrics can be used to define the size of a project?

    I. project completion time (PCT),

    II. budget,

    III. workload.

  13. 13

    Which of the following is not a part of the project closure plan?

  14. 14

    What are the three main factors generally used to evaluate the outcomes of a project? 

  15. 15

    Which of the symbols below represents the most likely time?

  16. 16

    Which of the followings represent true definitions about the calculations of the mean time and variance in PERT?

    1. The formula for the mean is a simple weighted average of the three estimates.
    2. The formula assumes that the optimistic and pessimistic estimates are equally possible.
    3. The formula assumes that the modal is four times more likely than the optimistic and pessimistic estimations. 
    4. The standard deviation is one-three of the range between optimistic and pessimistic time.
  17. 17

    An activity on arrow network includes 5 events, A, B, C, D and E. In that network, event C depends on event A and event B; event D and event E depend on event C. According to this, which of the following represent the precedence of the C? 

  18. 18

    Which of the followings is done in Monitoring and Controlling Process Group?

  19. 19

    ............................. is a non-simple, non-repetitive, one-time effort limited by budget, schedule and performance specifications designed to meet customer needs

    According to the definition, which of the following should come to the dotted point?

  20. 20

    Which of the following information is FALSE about CPM?