  1. 1

    I.   The Risk Records
    II.  Assumption Log
    III. Stakeholder Register

    Which of the above are inputs for qualitative risk analysis?

  2. 2

    With which of the risk avoiding strategy the risk does not disappear but shifts to the third party?

  3. 3

    What is an uncertain event or condition that, if it occurs, has a positive or negative effect on one or
    more project objectives?

  4. 4

    Which of the following are the true expressions about reducing the risk uncertainty?

    1. You need to eliminate the negative consequences.
    2. You must identify the likelihood and consequences of the risk.
    3. It is important to consider the risk's impact, and possible causes.
    4. Risks can not affect the scope, cost, time, and/or quality of projects.
    5. It is important to standardize the impact of risks in a common language for sharing the information to the stakeholders.
       
  5. 5

    In which quantitative risk analysis technique is it determined what variables in a system affect the system more?

  6. 6

    What is the last step in project risk management?

  7. 7

    "The project manager should also consider the impact thresholds for the risks. If the impacts exceed the specified thresholds, emergency plans are implemented. Thresholds may be in terms of money, duration, or number of resources based on tolerance." 

    According to this information, which of the scenarios below requires an emergency plan to be implemented?

  8. 8

    Which data analysis technique used for risk monitoring focuses on productrelated risks such as scope, functionality, and quality?

  9. 9

    Which of the following analysis is an analysis technique used to determine which variables in a system affect the system more?

  10. 10

    Which of the following is not one of the simple matric factors to perform the best way for a SWOT analysis?

  11. 11

    What is the expected cost of a project if the lowest estimates are $90,000, the most likely $170,000, and the worst $190,000 according to experts? 

  12. 12

    Which of the following techniques lists factors that have a definite impact on the project by examining the Strength, Weaknesses, Opportunities, and Threats?

  13. 13

    Which strategy is not used for responding to negative risks?

  14. 14

    Which of the following analysis  is the process of numerically analyzing the combined effect of identified individual project risks and other sources of uncertainty on overall project objectives?

  15. 15

    In which step of the risk management plan are strategies such as escalating, avoiding, transferring, mitigating or accepting negative risks identified?

  16. 16

    Which of the following is an explanation of how you plan to implement the project risk management plan?

  17. 17

    Which of the following includes reducing the likelihood of risk occurring or the effect of damage?

  18. 18

    Which of the following categories include 'the knowledge of project manager' in SWOT analysis?

  19. 19

    Which of the following strategy for positive risks or opportunities is aimed to find the best way to take advantage of the opportunity by eliminating the uncertainty in the project?

  20. 20
    1. Removal
    2. Transferring risk and insurance
    3. Mitigation