- 1
In order to avoid negative risks, Project Team A decides to work with Supplier X with whom they have worked before. This strategy is an example of ...............?
- 2
Which of the following has all of the inputs of Qualitative Risk Analysis completely?
- 3
Which of the following is to obtain a comprehensive list of individual project risks and sources of overall project risk?
- 4
What qualitative risk analysis tool includes technical, external, and internal risk groups, and identifies the areas that may affect the project the most and provides the right risk response plan?
- 5
Which of the following includes reducing the likelihood of risk occurring or the effect of damage?
- 6
Which of the following makes it possible to evaluate the threat value on the project as time and money?
- 7Which of the following are a part of the monitoring risk? Monitoring the implementation of agreed-upon risk response plans, Tracking identified risks, Identifying and analyzing new risks, Evaluating risk process effectiveness throughout the project, Developing the risk standardization
- 8
Which of the followings is included in the project management plan?
- The budget
- Potential cause groups
- Risk probability and impact levels
- The Project Risk Management Methodology
- 9
When agreeing with a supplier, selecting a supplier who has already worked with our company can reduce many risks. This is an example to a _________.
- 10
Which of the following are true expressions about the risk monitoring?
- Technical performance analysis is a very important in the risk monitoring process
- Reserve analysis aims to protect the budget and time by ensuring that its reserves are sufficient to meet these impacts.
- Work performance information, change requests, project management plan updates, project documentation updates, and corporate process assets updates are the outputs of the risk monitoring.
- Success of technical performance analysis depends on the team that determines the performance parameters at the beginning of the project.
- Monitor warning signs that risks may arise, control risks using identified responses, identify and analyze emerging risks.
- 11
Which of the following is used to determine which variables in a system affect the system more?
- 12
Which of the following is one of the tools or techniques of quantitative risk analysis?
- 13
What of the following is not one of the risk identification tools and techniques in project management?
- 14
Which of the following presents the risk identification technique that include the questions about the reasons of the risks and the conditions where the risk turn into a problem?
- 15
What is necessary in order to effectively monitor and control risks in a project?
- 16
Which of the quantitative risk analysis technique below is related to measuring how the system reacts under various conditions?
- 17
SWOT analysis lists factors that have a definite impact on the project. The best way to perform SWOT analysis is to create a simple matrix. The deficiencies of the sponsor, the project manager, or the project team are evaluated in which of the different factors of the matrix?
- 18
Which of the following is done to to obtain a comprehensive list of individual project risks and sources of overall project risk while identifying risks?
- 19
- Technical performance analysis
- Risk audits
- Reserve analysis
Which of the techniques above does data analysis in monitoring risk process include?
- 20
Which of the followings is NOT one of the outputs of risk monitoring?