    Project Team A agrees to work with Supplier X. The data shows that Supplier X failed to deliver in time, 3 times in the 45 projects they worked together. What is the Expected Monetary Value if the impact on the project is $60,000?

  2. 2

    I. Cost

    II. Likelihood

    III. Impact

    IV. Consequences

    Which of the aspects of the risk above must be considered to reduce uncertainty in projects?

  3. 3

    Which quantitative risk analysis is an analysis technique used to determine which
    variables in a system affect the system more?

  4. 4

    Which of the following is used to offset the impact of a risk on the scope, time, cost, or quality of a project?

  5. 5

    Which of the following is used used to identify important issues to consider and ensure that they are not
    omitted?

  6. 6

    Which risk identification technique can help you to see the many risks associated with the project in a short time with the participation of people with different backgrounds, perspectives and expertise? 

  7. 7

    Which of the following is used to describe the effect of variables by representing each risk and its impact by a bar?

  8. 8

    Which of the following is not among the tools that can be used to perform qualitative risk analysis?

  9. 9

    Which of the following is the process of defining how to conduct risk management activities for a project?

  10. 10

    Which of the followings is a schematic representation of several decisions followed by different chances of the occurrence, which makes it possible to evaluate the threat value on the project as time and money?