  1. 1

    "A temporary endeavor undertaken to create a unique product, service, or result" is the definition for:

  2. 2

    Which of the following may not be true for projects?

  3. 3

    In which step of resource management do we sum the resources that are required to complete all the activities with respect to the resource allocation step outputs?

  4. 4

    ............................. definition is the process of developing a detailed description of the project and product.

    Which of the following should come to the dotted point according to the continuation of the sentence?

  5. 5

    Which of the following are the main attributes that distinguish project management from traditional forms of management, i. e. the fundamentals of project management?

    • I. Stakeholders
    • II. Team
    • III. Scope
    • IV. Methodology
    • V. Outcome
    • VI. Manager
  6. 6

    Which of the followings are a part of the project definition?

    1. An activity with a specific and unique objective
    2. An activity with a start and end date
    3. An activity that have specific time, cost and performance requirements
    4. A project is a temporary endeavor under taken to create a unique product, service or result 
  7. 7

    Which of the following is a difference between project and program? 

  8. 8

    Which of the followings represent true definitions about the calculations of the mean time and variance in PERT?

    1. The formula for the mean is a simple weighted average of the three estimates.
    2. The formula assumes that the optimistic and pessimistic estimates are equally possible.
    3. The formula assumes that the modal is four times more likely than the optimistic and pessimistic estimations. 
    4. The standard deviation is one-three of the range between optimistic and pessimistic time.
  9. 9

    Which of the followings is NOT true for the characteristics of a project?

  10. 10

    Which of the following is not one of the evaluation factors of a project outcomes?

  11. 11

    I. Node

    II. Arrow 

    III. Activity

    Which of above is among the components of the network?

  12. 12

    I.    network planning

    II.   network implementation

    III.  network control 

    IV.   network scheduling

    Which of the above are the stages of the fundamental network assessment of the project?

  13. 13

    I.   Introduction
    II.  Staffing requirements
    III. Staff assignments
    IV.  Reassignment parts

    Which of the above are components of a good staffing management plan?

  14. 14

    Which of the following is not one of the services of the Project Management Institute?

  15. 15

    What does the pre-planning, scheduling and resource allocation method for maximizing the effectiveness mean?

  16. 16

    ....... are performed when one tries to define a logical dependency?

  17. 17

    How many kinds of data are required to describe a project?

  18. 18

    ............... is a temporary endeavor undertaken to create a unique product, service, or result.

    Which term can be used in the blank?

  19. 19

    What is the first phase of project life cycle which involves identification and specification of the project called?

  20. 20

    Which of the followings is NOT true for a project?