AÖF Soru Bankası
İSL358U

Project Management (ENG)

Deneme Sınavı Soruları

  • 20 soru
  • Cevap anahtarı açık: çöz, sonucunu gör
0 doğru · 0 yanlış · 20 kaldı
  1. 1
    Which of the following is FALSE about Work Breakdown Structure (WBS)?
  2. 2

    Which of the following phases of project life cycle typically takes the longest?

  3. 3

    Which of the following is a method for dividing the overall project into smaller elements that is called work packages?

  4. 4

    Which three factors are usually used to evaluate the outcomes of a project?

    • I- management
    • II- cost
    • III- monitoring
    • IV- schedule
    • V- methodology
    • VI- competition
    • VII- performance
  5. 5

    Which of the following is not provided to the project manager by the project management methodology between phases?

  6. 6
    According to the figure, which one is NOT a critical activity?
  7. 7

    Which of the following phases comes first in a project life cycle?

  8. 8

    Which of the following is NOT one of the principles to adopt when creating an AOA network diagram?

  9. 9

    Which of the followings is NOT true?

  10. 10

    Which of the following is not one of the project characteristics?

  11. 11

    ............... is a method for dividing the overall project into smaller elements that are called work packages?

  12. 12

    Which of the followings is NOT one of the the Four M’s, which is a common framework for defining the resources available for a project?

  13. 13

    Which of the followings are the stages in which the fundamental network assessment of the project is carried out?

    1. Network planning
    2. Network scheduling
    3. Network monitoring
    4. Network control
  14. 14

    Which of the following is wrong for work packages?

  15. 15

    ....... typically forms the lowest level in the Work Breakdown Structure?

  16. 16

    Which of the following is the first step in PERT analysis?

  17. 17

    The stages of design, production and implementation are included in which of the phases of a project life cycle?

  18. 18

    Which of the following represents the true definitions about comparison between "activity on arrow (AOA)" and "activity on network (AON)"?

    1. The dummy activities in AON representation are not necessary.
    2. AON can be drawn and read more readily.
    3. In AOA, activity can only begin once all of its predecessors have been completed.
    4. AON enables the depiction of overla /lag.
    5. AON enables four kinds of relationships to be represented while AOA enables only finish to start relationship. 
     
  19. 19

    At what step of resource management, can the dates of the tasks be delayed in order to overcome the overallocation of resources? 

  20. 20

    Which of the following step of Resource Management, known as the first step, aims to identify the types, amount, and characteristics of the resources needed to accomplish the activities?

Bir şıkka dokun; doğru cevap hemen görünür.
Yeni yılların sınavlarını da çözProject Management (ENG) dersinin tüm sınavları, cevap anahtarları, süreli mod ve yanlış analizi uygulamada.Uygulamada aç